Union Mulberry Drainage Improvements Phase III

Storm Sewer Manhole

FOR MORE INFORMATION CONTACT​:

DENISE CREWS, P.E.​
STORMWATER MANAGER​
121 E. CHESTNUT ST ​
SUITE 100​
LANCASTER, OH 43130​

(740) 687-6614


dcrews@ci.lancaster.oh.us
The City is awarding the contract to Trucco Construction Co., Inc. from Delaware, Ohio.  Construction has begun as of March 9, 2020 and is expected be completed in Fall 2020.  The tentative schedule is:

​Phase 1 Union Street                                                                    March 2020-July 2020
​Phase 2 Ohio Avenue                                                                   May 2020-October 2020
​Phase 3 Mulberry St/Kline Ct/Carl Dr                                           May 2020-November 2020
​Testing and Restoration                                                                November 2020-December 2020
​Sixth Avenue (Broad St to alley east of Maywood Avenue)          June 2020-July 2020
​Alley South of Sixth Avenue (Forest Rose Ave to Columbus St)   July 2020
​Testing and Restoration activities                                                  June 2020-September 2020

​This schedule is weather dependent and subject to change based on field conditions.

​Funding for this project is from the Stormwater Utilty.